Our process

At MD Construction, we believe transparency is essential for a smooth home improvement experience. Below you’ll find a clear breakdown of each step in our process, from securing permits and HOA approvals to completing your installation. We’ve included timeline estimates to keep you informed and confident throughout your project.

01

Administrative, Permitting, & HOA*

Create Job File

Design Job

Request Engineering

Email Drawings to Home Owner

Submit HOA Application

Submit for County Approval

Receive Approved Permit

Send Job to Production

Entire process can take 4 – 8 weeks depending on County and HOA

Some HOA’s will not allow ARC applications from Vendors
We will provide all requested paperwork for the homeowner to submit online, in person, or via your online HOA portal if necessary

Laptop showing our engineering plans for our process. Front lanai installation review. Screen enclosures. Screening a lanai. Screen enclosures near me. Sunrooms Orlando Florida. Poop Lanai. Sunroom Orlando fl. Lanai Patio enclosure. Patio enclosure suppliers. Patio cover with screen. Pool enclosure florida. patio cover screen. florida screened in porch. screen patio covers. pool screen enclosures florida. screen pool enclosures florida. patio screen enclosures near me. florida porches

all time frames are estimates and subject to change at any time

Step 2 Foundation in our process - photo of a concrete form ready to pour.. Front lanai installation review. Screen enclosures. Screening a lanai. Screen enclosures near me. Sunrooms Orlando Florida. Poop Lanai. Sunroom Orlando fl. Lanai Patio enclosure. Patio enclosure suppliers. Patio cover with screen. Pool enclosure florida. patio cover screen. florida screened in porch. screen patio covers. pool screen enclosures florida. screen pool enclosures florida. patio screen enclosures near me. florida porches

all time frames are estimates and subject to change at any time

02

FOUNDATION**

Remove Grass & Install Form Boards (& Rebar if required)

Termite Spray

Slab/Footer Inspection by County

Pour Concrete

For Concrete: Broom Finish or Texture / Paint

For Pavers: Install Pavers

Second Payment Due

Once started, foundation work can take up to 2 weeks pending unforeseen delays such as weather
Homeowner is responsible for irrigation

03

Installation**

Take Precise Measurements at Jobsite for Prefabrication

Pre-Fab in Our Warehouse

Schedule Installation Date

Install at Jobsite (Sunrooms see #4)

Third Payment Due at Start of Installation

Final Inspection by County

Final Concrete Paint (if applicable)

Final Payment Due

Installation are being scheduled 2 – 5 weeks AFTER all HOA & Permitting approvals (if no foundation) or 3 – 6 weeks AFTER Foundation completion

Step 3 our the process installation of a pool enclosure. Front lanai installation review. Screen enclosures. Screening a lanai. Screen enclosures near me. Sunrooms Orlando Florida. Poop Lanai. Sunroom Orlando fl. Lanai Patio enclosure. Patio enclosure suppliers. Patio cover with screen. Pool enclosure florida. patio cover screen. florida screened in porch. screen patio covers. pool screen enclosures florida. screen pool enclosures florida. patio screen enclosures near me. florida porches

all time frames are estimates and subject to change at any time

Our Process Step 4 Sunroom. Outside view of a finished sunroom. Front lanai installation review. Screen enclosures. Screening a lanai. Screen enclosures near me. Sunrooms Orlando Florida. Poop Lanai. Sunroom Orlando fl. Lanai Patio enclosure. Patio enclosure suppliers. Patio cover with screen. Pool enclosure florida. patio cover screen. florida screened in porch. screen patio covers. pool screen enclosures florida. screen pool enclosures florida. patio screen enclosures near me. florida porches

04

Sunrooms***

Take Measurements for Windows After Frame Install

Order Custom Windows

Schedule Electrical Rough

Electrical Rough & Framing Inspections by County

Install Windows

Schedule Electrical Trim

Final Inspections by County

Final Concrete Paint (if Applicable)

Final Payment Due

*Some cities require HOA approval BEFORE the permit application can be submitted.

**Foundations are currently scheduled 4–6 weeks AFTER ALL approvals have been received (HOA, permits, and plan approval). Screen walls installed under existing roofs do NOT require preliminary measurements and will NOT be prefabricated. Precise measurements are taken 1–2 weeks after the foundation is complete. Installation is currently scheduled 3–6 weeks AFTER foundation completion.

***Windows are custom-made to fit the installed frame. Measurements are taken once the frame installation is complete, and windows are ordered within 1–2 days. Production and shipping of windows currently take 12–14 weeks.